A surge relief valve at the pump discharge is the cheapest-looking answer to a pump-trip upsurge, and on the 12 km DN800 reference main it caps its own connection well. Set at 95 m — lower than a station could hold in service, so a best case — it holds the pump end at 96.3 m where the unprotected line reaches 165–190 m. Everywhere else, the main still falls to vapour pressure from end to end, and the peak along the line remains 127–143 m depending on how the cavity is modelled — straddling the 136 m PN16 allowable. On a line that separates, the valve belongs behind the real protection, not in front of it.

1 · What a relief valve is for

A surge relief valve (SRV) is a normally closed valve that opens when the pressure at its connection exceeds a set point, and discharges to atmosphere or a sump. It acts on high pressure only, so it cannot put water into a line whose pressure is falling, and at its own connection only, reaching the rest of the line only through the waves that node sends out [1, 2].

A hydropneumatic vessel feeds the downsurge and absorbs the upsurge; a flywheel keeps the column moving; a one-way surge tank feeds a high point. The relief valve is only a pressure cap, so the design question is not whether it can cap the pump end but where the pressures that exceed the pipe rating are generated [3]. On a line that separates, most of those places are far from the pump.

2 · Where the upsurge on a pump trip comes from

Every head change in a transient is tied to a flow change by the Joukowsky relation, with the pipe’s characteristic impedance \(B\):

\[ \Delta H \;=\; \frac{a}{g\,A}\,\Delta Q \;=\; B\,\Delta Q, \qquad B \;=\; \frac{1050}{9.81 \times 0.5027} \;=\; 212.9\ \text{s/m}^2 \]

On the reference main — 12 km of DN800 ductile iron K9 to ISO 2531 [4], wave speed 1,050 m/s, 0.70 m³/s at 1.39 m/s, flat profile — stopping the full flow is worth \(B \times 0.70\) = 149.1 m, but only 85.0 + 9.8 = 94.8 m is available above vapour at the pump. When every pump trips, the pump end drops straight to −9.8 m and the whole line is at vapour within 11.4 s. Then, in the vapour cavity model:

Why collapse peaks are quoted as ranges

The results come from a method-of-characteristics model with a vapour cavity model, cross-checked with a gas cavity model and an independent second code (120 reaches, 150 s runs). They are not HAMMER output; a project analysis must be run in HAMMER, or an equivalent package, on the real profile. Maxima that follow a collapse are quoted as a range across the two models, because the spike depends on how the cavity is represented: one closes a concentrated cavity in an instant, the other cushions the closure with a trace of free gas [1, 6]. Here the gas cavity model gives line maxima 10–13 % lower, an undersized valve’s pump-end peak about a fifth lower, and peak relief flows a third or more lower. A finer grid does not close the gap: at 95 m the line maximum moves by less than 1 m between 60 and 240 reaches, against about 17 m between the two models.

3 · Worked example: one valve, four settings

The valve is a spring-loaded relief valve on the pump discharge header, downstream of the check valves, discharging to atmosphere. It opens in proportion to the head above its set point and reaches full lift at an overpressure of 4 m. The discharge law, the usual form of a valve boundary in a characteristics model [7], is

\[ Q_r \;=\; C_d\,A\;\min\!\left(1,\;\frac{h - H_s}{\Delta h_{op}}\right)\sqrt{2 g h}, \qquad h > H_s \]

with \(h\) the head at the valve, \(H_s\) the set head, \(\Delta h_{op}\) = 4 m and \(C_d A\) for DN250 at \(C_d\) = 0.6. Three idealisations matter, and a project model must replace each: all pumps stop instantly behind an ideal check valve, with no rundown (the bounding case for the downsurge; a real rundown changes when and how hard the column returns); the valve has no dynamics — no opening delay, closing time or blowdown (section 9); and the nominal bore is taken as the flow area.

Three settings are modelled: 120 m, 110 m and 95 m. Read 95 m, only 10 m above the steady head, as the best case for the valve rather than a usable setting: it is below the shut-off head of the series’ model pump, so the valve would open in service (section 9).

DN250 relief valve at the pump, all pumps tripped. Results without collapse to 0.1 m; collapse-driven maxima as a range across the vapour and gas cavity models.
Set headPump-end max, vapour / gas model (m)Line max (m)Length above 136 m, vapour / gas (km)Line min (m)Peak relief flow, vapour / gas (m³/s)
No valve165–190165–19012.0 / 11.0−9.8
120 m120.9 / 120.5140–15511.9 / 3.9−9.80.319 / 0.179
110 m111.0 / 110.6133–15110.0 / 0−9.80.359 / 0.220
95 m (best case)96.3 / 95.9127–1431.6 / 0−9.80.416 / 0.280

The valve does its own job in every case, holding the pump end within 1.3 m of the set point. It does nothing for the minimum, −9.8 m throughout. The line maximum falls with the set point but never clearly below 136 m: over it under both models at 120 m, model-dependent at 110 m and 95 m. The peak relief flow at 95 m, 0.416 m³/s in the vapour cavity model, is 59 % of the pumped flow.

4 · Interactive: the pump end, second by second

Pick a setting and watch the head at the valve; the faint trace is the same trip with no valve.

Pressure head at the pump discharge after all pumps trip
Vapour cavity model time history; instant stop of all pumps; DN250 relief valve, Cd 0.6, full lift at set + 4 m, no opening delay. The line maximum readout spans both cavity models; the line minimum is the lowest head anywhere on the main.
Steady head at the pump 85.0 m; PN16 allowable 136 m.
Pump-end max
96.3 m (gas model 95.9)
Line max, two models
127–143 m
depends on the cavity model
Line min
−9.8 m
vapour: column separation
Peak relief flow
0.416 m³/s (gas model 0.280)
Valve first opens
47 s

At 95 m the pump end sits at vapour for 47 s; the valve opens the instant the cavity closes and holds 95.0–95.7 m. At 69 s, where the unprotected trace spikes to about 190 m (165–190 m across the two cavity models), the valve opens further and the head reaches 96.3 m. At 110 m and 120 m it opens part-way up the climb after the collapse. Every setting gives the same pattern: an excellent result at the valve in this no-delay model, −9.8 m on the line, and a line maximum the valve cannot settle.

5 · Why the line still fails — or might not

The valve removes the doubling at the check valve, which lowers the envelope near the pump: at 6 km the maximum falls from 150–160 m unprotected to 120–130 m at a 95 m setting. The far end is governed by the front that left the pump at 47 s at about 97 m — barely touched by a 95 m valve, and untouched by a 110 m or 120 m valve that has not yet opened. In the vapour cavity model the 120 m envelope matches the unprotected one from 8.0 km onwards, and the 110 m envelope from 10.7 km.

Then comes the model question. At 95 m the vapour cavity model peaks at 11.9 km and leaves the last 1.6 km above 136 m; the gas cavity model peaks lower, at 11.1 km, and leaves none. Honestly quoted, the line maximum is 127–143 m, with 136 m inside the range. Higher settings only lengthen the stretch over the allowable (table 1).

Not a design A scheme whose compliance hangs on the least certain number in transient analysis is not a design. Accept the 95 m valve because the gas cavity model shows 127 m, and a modelling option has chosen the pipe class — at a setting the station could not hold. Every high head on the line still comes from a column stopped after separation [6, 8]. Protect the downsurge, and the upsurge becomes a clean, well-predicted wave.

Why a lower set point cannot fix it

The set point cannot go below the pumps’ shut-off head plus a margin (section 9), and the governing front leaves the pump at about 97 m: \(B\) times the returning flow, counted up from vapour pressure. A relief valve set at or above that head barely touches it. Near the reservoir the same front is counted up from 44.8 m, which is why the envelope rises towards the delivery end. Only a device that stops the column separating removes the returning flow; a valve already open when it returns might discharge part of it (the anticipator, section 9).

6 · Interactive: along the line

The shaded band between the two maximum envelopes is the part of the answer that belongs to the cavity model rather than to the valve.

Maximum and minimum head envelopes along the 12 km main
Maximum envelopes from the vapour and gas cavity models, minimum envelope from the vapour cavity model, DN250 relief valve at the pump. The grey line is the vapour-model maximum with no valve.
Lengths count each 100 m reach whose maximum exceeds 136 m.
Above 136 m, vapour model
1.6 km
over the allowable
Above 136 m, gas model
0.0 km
within the allowable
Line max
127–143 m
Peak location, vapour / gas
11.9 / 11.1 km
Max at 6 km
120–130 m

At 95 m the upper edge of the band crosses 136 m over the last stretch before the reservoir and the lower edge does not; step through the settings to see the lengths in table 1 build up. Against the grey unprotected line, the valve pulls the envelope down near the pump and leaves the far end alone. The minimum envelope never moves.

7 · Sizing the valve: flow first, then bore

A relief valve is sized for a flow, and the flow is a transient result: at the 95 m setting, 0.416 m³/s in the vapour cavity model and 0.280 m³/s in the gas cavity model. The peak is collapse-driven too, so size for the larger.

A first estimate before the model

Without the valve the waves lift the pump end to the unprotected peak \(H_u\); with the valve open near \(H_s\), the flow behind the difference has to leave through it:

\[ Q_r \;\approx\; \frac{H_u - H_s}{B} \;=\; \frac{(165\ \text{to}\ 190) - 95}{212.9} \;=\; 0.33\ \text{to}\ 0.45\ \text{m}^3/\text{s} \]

The model gives 0.280–0.416 m³/s. The estimate runs 7–17 % high because each discharge weakens the waves that follow — the right side to err on when choosing sizes to model.

Capacity at full lift, Kv and Cv

Full lift is reached at the set head plus the overpressure, so the capacity at full lift, discharging to atmosphere, is

\[ Q_{cap} \;=\; C_d\,A\,\sqrt{2 g \left(H_s + \Delta h_{op}\right)} \]

— 1.298 m³/s for DN250 at a 95 m set head and \(C_d\) = 0.6, with the other sizes in the table. Manufacturers usually quote a flow coefficient, so convert the required flow at the set pressure, 95 m or 9.32 bar:

\[ K_v \;=\; \frac{Q\ [\text{m}^3/\text{h}]}{\sqrt{\Delta p\ [\text{bar}]}} \;=\; \frac{0.416 \times 3600}{\sqrt{9.32}} \;=\; 491\ \text{m}^3/\text{h}, \qquad C_v \;=\; 1.156\,K_v \;=\; 567 \]

The same law gives the head at the valve, \(h = H_s + \Delta h_{op}\,Q_r / (C_d A \sqrt{2gh})\): 96.3 m for DN250, 97.0 m for DN200 and 98.5 m for DN150 at the flows the model computes — its pump-end maxima to 0.1 m. Once the valve is big enough, its own characteristic sets the pump-end result.

Valve size sweep at a 95 m set head, Cd 0.6, full lift at 99 m; capacity against a required 416 L/s. Collapse-driven maxima as a range across the two cavity models.
ValveCapacity at full lift (L/s)Capacity ÷ requiredPeak relief flow, vapour / gas (L/s)Pump-end max, vapour / gas (m)Line max (m)
DN1002080.50242 / 219110–134127–143
DN1504671.12407 / 27498.5 / 97.4127–143
DN2008312.00413 / 27897.0 / 96.4127–143
DN2501,2983.12416 / 28096.3 / 95.9127–143
DN3001,8694.49418 / 28195.9 / 95.6127–143

DN100 is undersized: its capacity at full lift is half the requirement, and it passes 242 L/s only because the pump end climbs to 110–134 m, a collapse-driven range again because the valve has lost control. From DN150 up the pump end is controlled, and each size step buys less than 1.5 m. DN150 works near full lift, with no margin for a lower installed discharge coefficient or a slower valve, so in our judgement DN200 or DN250 is the choice. The last column never moves: the line maximum is indifferent to the size of the valve.

The discharge side

At 0.416 m³/s a DN250 outlet runs at 8.5 m/s, and the model discharges 3.3–4.4 m³ per trip at 95 m (vapour and gas cavity models) — one event, not a sump volume. The discharge pipe must not throttle the valve, the sump or return must take the peak flow and repeated trips without backing up, and a valve venting at over 9 bar needs a splash guard and safe access [3, 9].

8 · Interactive: sizing the valve

The left axis carries the transient sweep at 95 m; the right axis carries the capacity at full lift for your inputs, against the flow you require.

Relief valve size: capacity, flow coefficients and the transient sweep
Left axis: maximum heads from the transient sweep at set 95 m, Cd 0.6; circles vapour cavity model, triangles gas cavity model. Right axis: capacity at full lift CdA√(2g(Hs + 4 m)) for your inputs, the required flow, and the sweep’s peak relief flows. Kv at the set pressure; head at the valve from the proportional-lift law with 4 m overpressure.
Nominal bore taken as the flow area.
Steady head at the pump 85.0 m. The transient sweep stays at 95 m.
Use the installed value, with inlet and outlet pipework.
Default: peak relief flow from the transient model, DN250 at 95 m, vapour cavity model.
Capacity at full lift
1.298 m³/s
Kv required
491 m³/h
Cv required
567 US
Capacity ÷ required
3.12 ×
adequate
Head at the valve
96.3 m, lift 32 %
First estimate of flow
0.33–0.45 m³/s

At the defaults the valve has 1.298 m³/s at full lift, 3.12 times the requirement, and settles at 96.3 m, a third of the way to full lift. At DN150 the ratio falls to 1.12 and the head rises to 98.6 m, nearly wide open; at a discharge coefficient of 0.45, DN150 is no longer enough. Raising the set head lowers the first estimate but not the sweep, which stays at 95 m; how the set point moves the line maximum is in figure 2 and table 1 (127–143 m at 95 m, 140–155 m at 120 m).

9 · Set pressure, reseating and the anticipator

Choosing the set point

Too high a set point exposes more of the line (table 1). Too low, and the valve opens in service: it must clear a second pump starting, a control valve moving and, above all, a delivery valve closed against running pumps, which takes the pump end to the shut-off head. The model pump of the pump inertia article in this series has a zero-flow head of 105 m (100 m above a 5 m suction), so a 95 m valve would discharge whenever the flow was throttled below about 0.50 m³/s. In our judgement a setting that clears 105 m with the valve’s tolerance is nearer 110–120 m, which leaves 10.0–11.9 km above 136 m in the vapour cavity model (none to 3.9 km in the gas cavity model). In our practice the set point comes from a run of the normal operating events — their highest head plus the set-point tolerance — and the trip is rerun at that setting.

ISO 4126-1 supplies the vocabulary [10]. The overpressure is the rise above set pressure needed for full lift (4 m here); the reseating pressure is where the valve closes again, and the difference from the set pressure is the blowdown — too long and the valve dumps water after the transient, too short and it chatters. On the pipe side, EN 805 distinguishes the design pressure from the maximum design pressure, which adds a surge allowance [11]: set point plus overpressure must not exceed the maximum design pressure, and nor may the maximum envelope anywhere along the line.

Spring-loaded or pilot-operated

A direct-acting valve holds its disc shut with a spring; a pilot-operated valve uses a small pilot, sensing line pressure, to control the chamber above the main valve — conceptually, simplicity against closer control of set point and closing speed [2, 3]. Neither opens instantly, and here the valve first opens at the worst moment: at 95 m on the cavity collapse itself, a step of about 106 m in one time step; at 110 m and 120 m part-way up the climb that follows. Without the valve the pump end rises from 96.5 m at the collapse to 102.3 m by 48 s and 109.0 m by 49 s, so a valve that takes a second or two to open lets the head run up that climb and sends a higher front towards the far end. Model the manufacturer’s opening and closing times before relying on any number here.

The surge anticipator valve

A surge anticipator valve (SAV) opens on the initial low pressure after a trip, so it is already open when the return wave arrives, and then closes slowly [2, 12]. That removes the opening-time problem, but it neither prevents separation nor feeds the downsurge. Being open when the column returns, it may lower the collapse front that governs the far-end peak; that has to be shown by modelling it, including its behaviour while its connection is below atmospheric pressure — the question behind air admission. No anticipator was modelled here.

10 · Where a relief valve is the right answer

None of this makes the SRV a bad device, only one with a narrow job. In our judgement it fits in three places, and fails in a fourth:

All pumps tripped on the reference main: what each option does to the envelope. Collapse-driven maxima as a range across the two cavity models.
OptionLine min (m)Line max (m)What it protects
No protection−9.8165–190Nothing: column separation along the line
Relief valve DN250, set 95 m (best case)−9.8127–143The pressure side, at the valve
Flywheel, total I = 400 kg·m²+9.385.0Both sides, by keeping the column moving
Vessel 20 m³, 3.5 m³ gas, differential DN400 connection+4.3119.2Both sides, at the pump

The two options that stop the column separating remove the collapse upsurge and keep the maximum within the rating (119.2 m and 85.0 m). That is the argument of this series in one table, worked through in choosing surge protection on one pipeline.

11 · Setting it up in Bentley HAMMER

Field names differ slightly between HAMMER versions, so read them as descriptions of intent [13]. The HAMMER transient workflow and HAMMER transient tips cover the general run set-up.

  1. Build and check the steady state. Reservoir, Pump, Pipe and delivery Reservoir on the real profile, with each Pipe’s wave speed from the Wave Speed Calculator (wave speed).
  2. Define the trip. On the Pump: a pump trip (shut down) at time zero, pump and motor inertia from the datasheets, 4-quadrant characteristic curves (from specific speed if the manufacturer’s are not available), and the check valve on the pump with its closure time or delay.
  3. Run it unprotected for several times 2L/a (150 s here, against 22.9 s), with the computed time step, a tight wave speed adjustment tolerance and vapour pressure / column separation on. Read the profile (path) with maximum and minimum head envelopes: if the line reaches vapour, the relief valve is not the primary device.
  4. Fix the threshold pressure from normal operation. Run a pump start, a controlled stop, control valve movements and a delivery valve closed against running pumps. Set the threshold (set) pressure above the highest head at the pump discharge node by the valve’s set-point tolerance.
  5. Add the Surge Valve at the pump discharge node, downstream of the check valves, as a surge relief valve: the threshold pressure from step 4, size and discharge coefficient, and time to open and time to close (or the opening and closing characteristics) from the manufacturer. An instantaneous opening is only a bounding sensitivity, and this article’s figures come from a different model, so do not expect to reproduce them. Rerun the step 4 events with the valve in place and confirm it stays shut.
  6. Build the comparisons. At least three valve sizes around the first estimate from section 7 as separate scenarios, with any higher set points as alternatives above the step 4 value.
  7. Read the pump end. In the Transient Results Viewer, plot the time history at the valve node: the head should stay within the overpressure of the set point. Note when the valve first opens and, if your version reports it, the peak discharge.
  8. Read the whole line. Plot the profile (path) envelopes for every scenario, check the maximum against the pipe rating along the full length, and use the animation to see where the high heads are generated.
  9. Check the minimum separately. The relief valve does nothing for the downsurge; the minimum envelope must meet the design minimum (+3.0 m here) by other means, or every maximum on the line is a collapse result.
  10. Test whether the verdict holds. Rerun any scenario that separates with different column separation settings. If the verdict against the pipe rating changes, the protection must change. A finer time step checks convergence but will not remove the cavity-model uncertainty.

12 · Design checklist

In summary Even in the best case, set at 95 m, a DN250 relief valve holds the pump end at 96.3 m and discharges 0.280–0.416 m³/s at its peak. It does nothing for the downsurge: the line still reaches vapour from end to end, and its peak is 127–143 m, either side of the 136 m allowable depending on the cavity model. Size it for flow, set it from normal operation, and use it where the pressure is generated at the valve — or behind a device that stops the column separating.
Surge protection design series
  1. Wave speed: the number that sets the surge
  2. The differential orifice: empty freely, refill slowly
  3. Bladder, diaphragm or air-over-water vessel
  4. One-way surge tanks at the knee
  5. Surge relief valves: what a valve at the pump can protect
  6. Pump inertia and the flywheel
  7. Choosing surge protection on one pipeline
The sizing method itself is in Sizing the Hydropneumatic Surge Vessel.

References & standards

  1. Wylie, E.B. & Streeter, V.L. Fluid Transients in Systems. Prentice Hall, 1993 — method of characteristics, pump and valve boundary conditions, column separation and the discrete vapour and gas cavity models.
  2. Chaudhry, M.H. Applied Hydraulic Transients, 3rd ed. Springer, 2014 — surge relief valves, surge anticipator valves and their representation in transient models.
  3. Thorley, A.R.D. Fluid Transients in Pipeline Systems, 2nd ed. Professional Engineering Publishing, 2004 — surge control devices, relief valve types and practical application on pumping mains.
  4. ISO 2531 Ductile iron pipes, fittings, accessories and their joints for water applications — the K9 ductile iron main of the reference system.
  5. Parmakian, J. Waterhammer Analysis. Dover, 1963 — pump discharge lines after power failure, the returning wave at a closed check valve, and relief valves.
  6. Bergant, A., Simpson, A.R. & Tijsseling, A.S. “Water hammer with column separation: a historical review.” Journal of Fluids and Structures, 22(2), 2006 — why cavity collapse peaks depend on the cavity model, and the vapour and gas cavity models compared.
  7. Larock, B.E., Jeppson, R.W. & Watters, G.Z. Hydraulics of Pipeline Systems. CRC Press, 2000 — valve discharge boundaries and orifice-type discharge laws in characteristics models.
  8. Swaffield, J.A. & Boldy, A.P. Pressure Surge in Pipe and Duct Systems. Avebury Technical, 1993 — pressure surge following column separation and the limits of local pressure relief.
  9. Stephenson, D. Pipeline Design for Water Engineers, 3rd ed. Elsevier, 1989 — protection of pumping lines, where relief valves suit and where they do not, and discharge arrangements.
  10. ISO 4126-1 Safety devices for protection against excessive pressure — Part 1: Safety valves — terminology: set pressure, overpressure, reseating pressure and blowdown.
  11. EN 805 Water supply — Requirements for systems and components outside buildings — design pressure, maximum design pressure including surge, and the surge allowance.
  12. Boulos, P.F., Karney, B.W., Wood, D.J. & Lingireddy, S. “Hydraulic transient guidelines for protecting water distribution systems.” Journal AWWA, 97(5), 2005 — surge relief and surge anticipating valves among the protection options, and their limits.
  13. Bentley Systems. OpenFlows HAMMER product documentation and help — Surge Valve, Pump and Pipe properties, transient run options and the Transient Results Viewer.
#SurgeReliefValve #SurgeAnticipatorValve #WaterHammer #HydraulicTransients #SurgeAnalysis #PumpTrip #PumpStations #ColumnSeparation #VapourCavity #CavityCollapse #MethodOfCharacteristics #Joukowsky #TransmissionMains #DuctileIron #PN16 #ReliefValveSizing #FlowCoefficient #Kv #Cv #SetPressure #Blowdown #BentleyHAMMER #OpenFlowsHAMMER #SurgeProtection #HydropneumaticTank #PipelineDesign #WaterSupply #EN805 #TransientModelling