A power failure stops a pump in a second or two; a variable-speed drive can take as long as the designer asks. On the unprotected 12 km reference main, ramping the pump to zero speed in 10 s still takes the line to vapour; 20 s leaves it at −5.0 m; 31.2 s, about 1.4 times 2L/a, is the shortest ramp that keeps every point at +3.0 m or above. Starting the same pump is almost harmless here, whatever the ramp: the head never exceeds about 102.5 m, because a pump cannot deliver more than its shut-off head. This article shows how to size stop and start ramps and pump control valve times from the model, why the flow stops long before the speed reaches zero, and which interlocks to write, while remembering that none of it helps when the power fails.

1 · Normal operations are surge events too

A pumped main sees a few power failures a year and thousands of normal starts and stops. Each normal event is a transient, and three things make them matter [1][2]:

The examples use the series' reference main without protection: 12 km DN800 ductile iron, 2L/a = 22.9 s, a pump with a 100 m shut-off rise above a 5 m suction, delivering 0.70 m³/s against a 44.8 m reservoir [3]. The network solver prescribes the pump speed (a drive ramp) or the opening of a pump control valve; it uses a vapour cavity model and has been verified against the series solver to 0.01 m.

2 · Stopping: how long a ramp?

A drive ramping the speed down linearly from full to zero over \(T_r\) decelerates the column gradually. The model gives the lowest head on the line for each ramp:

Stop ramp against the lowest head on the line
Upper: lowest pressure head on the line for a linear speed ramp from full speed to zero, unprotected reference main, 200–250 s runs. Points at −9.8 m are vapour. Lower: pressure head at the pump and at mid-line for the selected ramp.
2L/a = 22.9 s on this main.
Check it against the project's allowable values.
Lowest head, this ramp
–
Where
–
Highest head
–
Shortest ramp meeting the minimum
–
As a multiple of 2L/a
–

The shortest ramp is found between the computed points by interpolation; at +3.0 m a bisection on the model itself gives 31.2 s. Ramps of 0 and 10 s take the line to vapour, 20 s to −5.0 m, 40 s to +4.4 m. Beyond about two minutes each extra minute buys only a few metres. The maximum never exceeds the steady 85 m: a controlled stop of a pump with a check valve has no upsurge of its own.

3 · The flow stops long before the speed does

A centrifugal pump cannot deliver against a head higher than its shut-off head at that speed, which falls with the square of the speed. The pump stops lifting water into the line when [4][5]

\[ H_{suc} + H_0\,w^2 = H_{res} \quad\Rightarrow\quad w_0 = \sqrt{\frac{H_{res} - H_{suc}}{H_0}} = \sqrt{\frac{44.8 - 5.0}{100}} = 0.631 \]

On a linear ramp to zero, the pump has done its useful work after the first 37 % of the ramp: a 60 s ramp is in effect a 22 s deceleration of the column. Drives that ramp to a minimum speed rather than to zero, and pumps with a high static lift, make this worse. When specifying a stop ramp, think of the time from full speed to \(w_0\), not to zero; some drives allow a two-stage ramp (fast to just above \(w_0\), slow through it) for exactly this reason.

Where the pump stops delivering
Pump curves \(H = H_{suc} + H_0 w^2 - kQ^2\) at several speeds, and the system curve \(H = H_{res} + R Q^2\), with \(k\) and \(R\) set so the full-speed curve meets the system at the duty flow. The pump stops delivering at the speed whose shut-off head equals the static head.
Delivery level minus suction level.
Above the suction.
Static head plus friction at duty.
Speed at zero flow
–
Share of a linear ramp used
–
A 60 s ramp decelerates the flow in
–

4 · Starting: drive ramp or pump control valve

A start accelerates the column from rest. A drive ramps the speed up; a fixed-speed pump starts direct on line against a pump control valve that opens over a set time. In both cases the pump's head cannot exceed its shut-off head, 105 m at the pump here, so the start cannot produce a maximum above that unless air or vapour is in the line. On this main both kinds of start, at every ramp or opening time from 1 to 90 s, give a maximum of 99–102.5 m and no fall below the static 44.8 m [2][6].

Starting the pump into a full, still line
Pressure head at the pump and at mid-line, and the pump flow, for a drive ramp from zero to full speed or a direct-on-line start against a valve opening linearly (loss coefficient \(K_0/\tau^2\), \(K_0\) for 0.5 m at duty). Unprotected reference main, 200 s.
Same pump, same line.
From standstill or closed.
Highest head
–
Lowest head
–
Flow reaches 99 % at
–
Pump shut-off head
105.0 m

The start's maximum is set by the shut-off head, not by the ramp: a slower ramp only delays the column's acceleration. The real risk at a start is elsewhere: air at high points after a drain-down (see filling and restart), a check valve that opens late and lets the column slam it open, or starting into a column still oscillating after the previous stop.

5 · Settings and interlocks to write from the model

6 · Setting it up in Bentley HAMMER

Field names differ slightly between versions [7].

  1. Model the controlled stop as a variable-speed pump with a speed pattern ramping from 1 to 0 over the ramp time (or the pump's own speed-controlled transient setting in your version), not as a pump shutdown, which HAMMER treats as a trip.
  2. Model the start as a pump start with a speed ramp, or as a pump with a downstream control valve whose opening follows the specified time.
  3. Create one scenario per ramp and use batch run to bracket the shortest ramp that passes.
  4. Start from the right initial state: a full line at rest for a start, the duty point for a stop.
  5. Record the recurring pressure swing at the critical points for the fatigue check of plastic pipes.
  6. Write the settings into the control philosophy with the scenario that justifies each.

7 · Checklist

Surge analysis practice series
  1. Is your HAMMER run right? Time step, adjustment and run duration
  2. Validating a surge model with a field pump-trip test
  3. Sensitivity and uncertainty: bounding the result
  4. Pump data for a pump trip: inertia, specific speed and four-quadrant curves
  5. Demands, branches and dead ends in a transient model
  6. Reading the surge envelope against the pipe's real limits
  7. Transient forces on pipe supports and bends
  8. Booster stations in series
  9. Pump starts, controlled stops and drive ramps
  10. Filling, draining and restarting a transmission main
  11. Surge in wastewater force mains
  12. The surge study report: what to deliver and what a reviewer checks
The protection devices themselves are covered in the surge protection design series.

References & standards

  1. Boulos, P.F., Karney, B.W., Wood, D.J. & Lingireddy, S. “Hydraulic transient guidelines for protecting water distribution systems.” Journal AWWA, 97(5), 2005: pump start-up and shutdown transients, valve operation and control.
  2. Thorley, A.R.D. Fluid Transients in Pipeline Systems, 2nd ed. Professional Engineering Publishing, 2004: pump starting and controlled stopping, and their effect on surge.
  3. Abokhatwa, M. Surge protection design series, abokhatwa.com, 2026: the reference main, its pump and the verified MOC solver.
  4. Karassik, I.J., Messina, J.P., Cooper, P. & Heald, C.C. Pump Handbook, 4th ed. McGraw-Hill, 2008: affinity laws and the operation of variable-speed pumps against static head.
  5. Europump & Hydraulic Institute. Variable Speed Pumping: A Guide to Successful Applications. Elsevier, 2004: minimum speed against static head and drive ramp settings.
  6. Wylie, E.B. & Streeter, V.L. Fluid Transients in Systems. Prentice Hall, 1993: pump boundary conditions with prescribed speed and valve opening.
  7. Bentley Systems. OpenFlows HAMMER documentation: variable-speed pumps, pump start and shutdown, valve operating rules, scenarios and batch run.
#SurgeAnalysis #WaterHammer #VFD #VariableSpeedDrive #PumpStart #PumpStop #RampTime #PumpControlValve #Interlocks #ControlPhilosophy #AffinityLaws #BentleyHAMMER #TransientAnalysis #PumpStation #WaterEngineering