| Symbol | Value / unit | What it is |
|---|---|---|
| √3 | = 1.732 | The three-phase factor. |
| P / S / pf | kW / kVA / 0–1 | Real power / apparent power / power factor. S = P ÷ pf. |
| V / I | volts / amps | Line voltage / current. |
| %Z | e.g. 6% | Transformer impedance — limits fault current. |
| E / Φ / UF / MF | lux / lumens / 0–1 / 0–1 | Target light level / lamp output / utilisation & maintenance factors (lumen method). |
Key formulas: current I = S ÷ (√3·V) · fault Ifault ≈ Ifull-load ÷ (%Z÷100) · volt-drop Vd = (mV/A/m × I × L) ÷ 1000 · luminaires N = (E·A) ÷ (Φ·UF·MF)
4.1 Load estimate & demand
Role: total the connected load, apply diversity/demand factors, and add spare capacity — this sizes the supply, transformers and generators.
Worked example 4.1 · Building maximum demand
4.2 HV intake & substation
Role: the utility (e.g. SEC) delivers at high/medium voltage (e.g. 13.8/33 kV) into the building's main substation — HV switchgear, metering, protection. Tens of MVA can only enter at HV; bringing it in at LV would need impossibly large cables.
4.3 Transformers
Role: step MV down to LV (400/230 V). Distributed as unit substations on plant floors up the tower (dry-type/cast-resin indoors for fire safety). Sized in kVA with N+1.
Worked example 4.3 · Transformer count
4.4 Main LV switchgear & fault level
Role: the main LV board distributes transformer output to risers, with protective devices (ACBs/MCCBs) whose breaking capacity must exceed the prospective short-circuit current. Type-tested assemblies to IEC 61439.
Worked example 4.4 · Fault level & breaker duty
4.5 Risers & busbar trunking (busways)
Role: carry power up the tower from substations to floor boards. Large vertical feeders use busbar trunking (busway) with floor tap-offs — compact, fire-rated, and easy to tap, far better than bundles of cables in a tall riser.
4.6 Cable / feeder sizing — current, volt-drop, fault
Role: size every feeder for three checks: current-carrying capacity (with derating), voltage drop, and short-circuit withstand. In a tall building, voltage drop on long risers is the tough one.
Worked example 4.6 · Feeder current & volt-drop check
4.7 Distribution boards & final circuits
Role: floor/zone distribution boards split power into final circuits (lighting, sockets, mechanical, etc.), each protected by an MCB/RCBO sized to the cable and load, with earth-fault/RCD protection for socket and wet-area circuits.
4.8 Standby power — generators & UPS
Role: keep life-safety and essential loads running when the grid fails — fire pumps, smoke-control fans, firefighting lifts, emergency lighting, fire alarm, BMS, and selected services. Diesel generators (with fuel storage) provide standby; UPS bridges the gap and protects critical/IT loads with no break.
Worked example 4.8 · Generator sizing for essential load
4.9 Lighting — the fitting in the room
Role: deliver the design illuminance (lux) at the right quality (uniformity, glare UGR, colour) and low energy. Plus emergency lighting on escape routes. Designed by the lumen method, then verified by point calculation.
Worked example 4.9 · Lumen method (office)
4.10 Earthing & lightning protection
Role: a building-wide earthing/grounding system (equipotential bonding, earth electrodes, low earth resistance) for safety and equipment, plus a lightning protection system (LPS) — essential on a very tall structure that is a prime strike target.
| System | Design point | Code |
|---|---|---|
| Earthing/grounding | Low earth resistance, full equipotential bonding, dedicated clean earth for IT | IEC 60364-5-54, IEEE 142/1100 |
| Lightning protection | Air terminals/mesh, down-conductors, ring earths; protection level from risk assessment | IEC 62305 / NFPA 780 |
| Surge protection (SPD) | At intake & sub-boards to protect electronics | IEC 62305-4 / IEC 61643 |
4.11 Installation, accessories & field tricks
| Item | Field rule / trick |
|---|---|
| Cable containment (tray/ladder/trunking/conduit) | Size for ~40% fill + spare; segregate LV/ELV/fire cabling to avoid interference. |
| Fire-rated & fire-survival cabling | Life-safety circuits (fire pumps, smoke fans, FA) on fire-rated cable maintaining circuit integrity. |
| Firestopping at penetrations | Tested/listed firestop at every rated-barrier crossing (busways & trays). |
| Busway expansion & seismic support | Expansion units for building movement; bracing per SBC 301. |
| Labelling, phase identification, as-builts | Clear circuit schedules & labelling for safe maintenance. |
| Segregation of services in risers | Keep power away from sensitive ELV/data; bond cable armour & trays. |
| Spare ways & capacity | Leave ~20–25% spare ways in boards & containment for future loads. |
4.12 Testing & commissioning
- Insulation resistance, continuity, earth-loop & RCD tests; phase rotation; polarity.
- Functional tests: generator auto-start & load transfer (ATS), UPS autonomy, protection settings (per the coordination study), busway integrity.
- Integrated tests with fire (generators feeding fire pumps/smoke fans), witnessed for AHJ sign-off.
Terms & abbreviations
Plain-English meaning of the electrical terms used in this module.
| Term | What it means (plain English) |
|---|---|
| HV / MV / LV | High / Medium / Low Voltage. Power enters at HV/MV and is stepped down to LV (400/230 V) for use. |
| kW / kVA / pf | kW = real power (does work); kVA = apparent power (what the kit must be rated for); power factor (pf) = kW ÷ kVA. |
| √3 (root-3) | The 1.732 factor in three-phase power: P = √3 · V · I · pf. |
| Demand / diversity factor | Not all loads run at once — diversity reduces the connected total to a realistic maximum demand. |
| Transformer | Device that changes voltage (MV→LV); rated in kVA. |
| Impedance (%Z) | A transformer's internal resistance to fault current; sets how big a short-circuit can be. |
| Fault level / breaking capacity (kA) | The short-circuit current that could flow; breakers must safely interrupt at least this much. |
| Switchgear | The assembly of breakers/protection that distributes and protects circuits. |
| ACB / MCCB / MCB / RCBO / RCD | Types of circuit breaker / earth-fault protection, from large (ACB) to final-circuit (MCB), with RCD/RCBO adding shock protection. |
| Busway / busbar trunking | A compact prefabricated power "highway" up a riser, with tap-off points per floor. |
| Voltage drop | The voltage lost along a cable; kept within limits (~4%) so equipment gets enough voltage. |
| Ampacity / derating | A cable's safe current; reduced ("derated") for heat, grouping and installation conditions. |
| Generator (genset) / ATS | Standby engine-generator; ATS = Automatic Transfer Switch that switches loads to it on power loss. |
| UPS | Uninterruptible Power Supply — battery system giving no-break power to critical loads. |
| Essential / life-safety loads | Loads that must keep running on standby power (fire pumps, smoke fans, firefighting lifts, emergency lighting). |
| Lux / lumen method | Lux = light level on a surface; the lumen method calculates how many luminaires give the target lux. |
| UF / MF / UGR / LPD | Utilisation & Maintenance Factors (lighting efficiency), Unified Glare Rating, Lighting Power Density (energy limit). |
| Earthing / grounding & bonding | Connecting metalwork to earth for safety so faults trip protection and people aren't shocked. |
| LPS / SPD | Lightning Protection System / Surge Protection Device — protect the structure & electronics from strikes/surges. |
| NEC / IEC | The US (NFPA 70) and international (IEC 60364) electrical installation code families; SBC 401 is NEC-based. |
References & software map
| Task | Software | Code |
|---|---|---|
| Load-flow, cable & transformer sizing, fault & protection | ETAP, SKM PowerTools, DIgSILENT | IEC 60364, 60076, 61439, 60947; SBC 401 |
| Lighting design & LPD | DIALux evo, Relux | EN 12464-1; ASHRAE 90.1 / SBC 601 |
| Containment routing & coordination | Revit MEP + Navisworks | IEC 60364-5; SBC 401 |
| Lightning risk & LPS | Risk tools to IEC 62305 / NFPA 780 | IEC 62305 / NFPA 780 |
- SBC 401 — Saudi Electrical Code (NEC-based); SBC 601 — Energy; SBC 801 — Fire.
- IEC 60364 (LV installations), 60076 (transformers), 61439 (assemblies), 60947 (switchgear), 60364-5-52 (cables).
- NFPA 70 (NEC); NFPA 110/111 (standby/UPS); NFPA 101 (life safety); NFPA 780 / IEC 62305 (lightning).
- SEC distribution code; IEEE 142/1100 (earthing/power quality); EN 12464-1 (lighting); SASO efficiency.