| Symbol / constant | Value | What it is |
|---|---|---|
| ρ (water) | 1000 kg/m³ | Density of water — fixed property. |
| g | 9.81 m/s² | Gravity — fixed constant (pump-power formula). |
| cp (water) | 4.187 kJ/kg·K | Specific heat of water (hot-water heater duty). |
| η (eta) | 0.70 typical | Pump efficiency (decimal) — from the Given. |
| a | ≈ 1200 m/s | Pressure-wave speed in a steel water pipe (water-hammer formula). |
| 1 bar | ≈ 10.2 m water | Pressure-to-head conversion. |
| Water flow | 1 kg/s ≈ 1 L/s | Because ρ ≈ 1000 kg/m³. |
Key formulas: pump power P = ρ·g·Q·H ÷ η · heater duty Q = ṁ·cp·ΔT · pipe size A = Q ÷ v · surge ΔP = ρ·a·v
2.1 Water demand & design criteria
Role: establish how much water the building needs, instantaneously and per day. Everything downstream (tanks, pumps, pipes) is sized from this.
Method — two demands
- Average daily demand (m³/day) — for storage & utility sizing, from per-capita / per-key figures.
- Peak instantaneous demand (L/s) — for pipe & pump sizing, from the loading-unit / fixture-unit method (probabilistic — not all fixtures run at once). The fixture-unit total converts to a design flow via a Hunter-type curve.
Worked example 2.1 · Daily demand, a residential/hotel tower
2.2 The source — incoming supply & storage tanks
Role: the city main rarely has the pressure or steady flow a tower needs, so water is taken into ground-level storage tanks (a buffer + fire reserve), then pumped up. Storage smooths utility supply and gives resilience.
| Tank | Sizing guide |
|---|---|
| Domestic ground/break tank | ~0.5–1.0 day of average demand (authority rules vary); divided into 2 compartments for cleaning |
| High-level / roof tanks | Buffer for gravity zones + booster suction; sized for peak duration |
| Fire reserve | Separate dedicated volume (see Fire module) — never share with domestic draw-off below the fire level |
Worked example 2.2 · Domestic storage
2.3 Transfer pumps
Role: lift water from the ground tanks to high-level / zone tanks up the tower. Usually duty/standby, level-controlled (start/stop on tank floats), often staged for tall buildings.
Worked example 2.3 · Transfer pump duty
2.4 Pressure zoning — the tall-building core
Role: limit static pressure at fixtures (codes cap it, e.g. ≤ ~5 bar at a fixture) and guarantee a minimum residual at the highest tap. The tower is split into zones (~10–15 floors) fed by either gravity from a high tank through PRVs, or boosted up from a break tank — see Module 0.
| Parameter | Typical limit | Code |
|---|---|---|
| Max static pressure at a fixture | ≤ ~5 bar (PRV needed above) | SBC 701 / IPC |
| Min residual at highest fixture | ~1.0–2.0 bar (fixture/flush-valve dependent) | Manufacturer / SBC 701 |
| Zone height | ~10–15 floors | From the two limits above |
2.5 Booster pump sets (variable speed)
Role: raise pressure to feed a zone from a break tank, maintaining constant outlet pressure as demand varies, via a VFD-controlled multi-pump set (e.g. 3 pumps + standby) holding a pressure set-point.
Worked example 2.5 · Booster set for a zone
2.6 Pipe sizing & material
Role: deliver peak flow at acceptable velocity (noise & erosion) and pressure loss.
| Service | Velocity | Material (typical) |
|---|---|---|
| Cold-water mains/risers | 1.5–2.4 m/s | Galvanised/SS, HDPE, PPR, copper |
| Hot-water & recirc | ≤ 1.0–1.5 m/s (erosion-corrosion) | Copper / SS / PPR (temperature-rated) |
| Branch to fixture | ≤ 2.0 m/s | — |
Worked example 2.6 · Size a zone riser
2.7 Hot-water generation, circulation & Legionella
Role: generate hot water (calorifiers/water heaters, often fed by the central plant, heat pumps, or solar pre-heat) and keep it hot at every outlet via a recirculation loop — while controlling Legionella, a real life-safety issue in hotels.
Design method
Heater output: Q = ṁ · cp · ΔT. Storage + recovery sized on the hot-water demand profile. Recirculation flow sized to replace pipe heat loss so the return stays hot.
Worked example 2.7 · Water-heater duty
2.8 Valves, protection & accessories
- PRVs — cap zone pressure; often duplex (duty/standby) on risers.
- Backflow preventers / air gaps — protect potable water from contamination (essential at tank inlets, irrigation, cooling make-up).
- Check, isolation & drain valves; strainers.
- Water-hammer arrestors / surge vessels — absorb pressure spikes from fast-closing valves (flush valves, solenoids).
- Pressure/level gauges, water meters (sub-metering per zone/tenant).
Worked example 2.8 · Water hammer (why arrestors are not optional)
2.9 Soil, waste & venting
Role: carry foul water down to the sewer by gravity, while the vent system keeps air pressure in the stack near atmospheric so trap seals aren't siphoned or blown out. In tall stacks this is a serious design issue.
Method
Stacks sized by drainage fixture units (DFU) per code. Tall stacks need offsets, vent design, and pressure-attenuation because falling water builds pressure transients.
| Issue in tall stacks | Solution |
|---|---|
| Pressure transients (siphon trap seals) | Properly sized stack + vent; PAPA (positive air pressure attenuators) & AAVs where allowed |
| Terminal velocity / energy at base | Large-radius offsets, relief vents at offsets, robust base bend |
| Trap seal loss | Deep-seal traps; vent every branch per code |
Worked example 2.9 · Stack & vent sizing (concept)
2.10 Rain / storm-water drainage
Role: drain roofs, terraces and podiums. Two methods: conventional gravity (sloped, air in pipe) or siphonic (full-bore, self-priming — fewer, smaller pipes, ideal for large roofs). Sized on rainfall intensity × area.
Worked example 2.10 · Roof rainwater flow
2.11 Fixtures & terminals — the last piece
Role: the sanitaryware and outlets the user touches — WCs, basins, showers, bidets, kitchen/F&B and laundry connections. Each has a design flow and a water-efficiency rating.
| Fixture | Typical design flow / use | Efficiency lever |
|---|---|---|
| Wash basin tap | 0.1–0.2 L/s | Aerators / flow restrictors (~6 L/min) |
| Shower | 0.1–0.2 L/s | Low-flow heads (~9 L/min) |
| WC | Dual-flush 3/6 or 4.5 L cisterns; flush valves need high flow | Dual-flush / low-volume |
| Kitchen / F&B / laundry | Per equipment schedule | — |
2.12 Water reuse & treatment
Role: reduce potable demand and meet sustainability targets via greywater recycling (showers/basins → treated → toilet flushing/irrigation), condensate recovery (large in humid climates — AHU/FCU condensate is clean water), and water treatment (softening, filtration) to protect equipment.
2.13 Installation, accessories & field tricks
| Item | Purpose / field rule |
|---|---|
| Pipe supports/hangers, anchors & guides | Spacing per material (plastic sags more than metal — closer supports); allow thermal movement on hot & long runs. |
| Expansion provision | PPR/HDPE expand a lot with temperature — fit expansion loops/arms; rigid anchoring cracks fittings. |
| Access & rodding points | At stack bases, offsets & changes of direction for drain clearing. |
| Trap seals (deep seal in tall stacks) | Use 75 mm seals; vent properly so they aren't siphoned. |
| Sleeves + firestopping; puddle flanges in wet areas | Fire-rated penetrations sealed with tested systems; waterproofing at slab penetrations. |
| Insulation (anti-condensation on cold; heat on hot) | Cold pipes in humid risers sweat — insulate & vapour-seal. |
| Dielectric unions between dissimilar metals | Prevent galvanic corrosion (e.g. copper to steel). |
| Isolation valves per zone/branch/wet-area | So one bathroom can be isolated without draining the riser. |
| Trace heating (where needed) & UV protection on roof pipes | Field detailing for reliability. |
2.14 Testing & commissioning
- Pressure test all pipework (hydrostatic) before concealment; drainage tested by water/air & ball test.
- Disinfect potable system (chlorination), flush, and sample water quality before handover.
- Balance hot-water recirculation (confirm ≥55 °C return at index outlet); set PRVs and booster set-points; verify residuals at the highest fixtures.
Terms & abbreviations
Plain-English meaning of the plumbing terms used in this module.
| Term | What it means (plain English) |
|---|---|
| PHE | Public Health Engineering — the plumbing/drainage discipline. |
| Loading / fixture units (LU / FU) | A weighting given to each tap/fixture so you can estimate the likely simultaneous demand (not everyone uses water at once). |
| Hunter curve | The curve that converts total loading units into a probable design flow — it flattens as fixtures increase. |
| Demand (daily vs instantaneous) | Daily demand (m³/day) sizes storage; peak instantaneous flow (L/s) sizes pipes & pumps. |
| Break tank | An open tank that resets water pressure to atmospheric before re-pumping a higher zone. |
| Booster set | A multi-pump, variable-speed package that raises pressure to feed a zone. |
| Transfer pump | Pump that lifts water from low tanks to high-level tanks. |
| Residual pressure | Pressure still available at the highest/furthest fixture after losses. |
| PRV | Pressure-Reducing Valve — caps pressure so low-zone fixtures aren't over-pressured. |
| Recirculation (HW) | A loop that keeps hot water moving so every tap gets hot water quickly. |
| Legionella | Bacteria that grow in stagnant warm water; controlled by storing ≥60 °C and returning ≥55 °C. |
| TMV | Thermostatic Mixing Valve — blends hot & cold at the outlet to prevent scalding (~43 °C). |
| Backflow / air gap | Protection stopping used/contaminated water flowing back into the clean supply. |
| Water hammer / Joukowsky | A pressure spike when flow stops suddenly; the Joukowsky equation estimates it. Arrestors absorb it. |
| NPSH | Net Positive Suction Head — the suction condition a pump needs to avoid cavitation. |
| Soil / waste / vent stack | Soil = toilet drainage; waste = basins/showers; vent = pipes keeping air pressure stable so traps aren't siphoned. |
| DFU | Drainage Fixture Units — used to size drainage stacks from code tables. |
| Trap seal | The water held in a U-bend that blocks sewer gases; can be lost if the stack isn't vented properly. |
| PAPA / AAV | Positive Air Pressure Attenuator / Air Admittance Valve — devices that manage air pressure in tall drainage stacks. |
| Siphonic drainage | Full-bore, self-priming rainwater drainage — fewer/smaller pipes for big roofs. |
| Greywater / condensate reuse | Recycling lightly-used water (showers/basins) or AHU condensate for flushing/irrigation. |
References & software map
| Task | Software | Code/standard |
|---|---|---|
| Demand / loading units / pipe sizing | Revit MEP; spreadsheets to code tables | SBC 701; IPC/UPC; BS EN 806; CIBSE Guide G |
| Pressurised network & pump duty | AFT Fathom | Hydraulic Institute; SBC 701 |
| Transient / surge (water hammer) | AFT Impulse; Bentley HAMMER | Joukowsky; engineering practice |
| Pump / booster / heater selection | Grundfos, Wilo, Lowara, calorifier/heat-pump tools | NPSH (HI); SBC 601 |
| Drainage & venting; siphonic storm | Revit + plug-ins; supplier tools (PAPA/siphonic) | SBC 701; EN 12056; IPC/UPC |
- SBC 701 — Saudi Sanitary (Plumbing) Code; SBC 601 — Energy; 2018.
- IPC / UPC; BS EN 806 (supply); BS EN 12056 (drainage incl. siphonic).
- ASHRAE 188 & CIBSE TM13 / HSG274 (Legionella); CIBSE Guide G (Public Health).
- NSF/ANSI 61 (potable contact); ASSE backflow series; EPA WaterSense; SASO/GSO water quality.
- MSS SP-58 (supports); Hydraulic Institute (pumps/NPSH); NWC/MEWA local requirements.