A mixed-use tower puts restaurants on the podium, a signature dining floor near the top, and staff kitchens somewhere in between — and every one of them needs a duct that runs, unbroken and uninterrupted, from the hood to the roof. That duct is lined with a combustible deposit, passes through occupied floors for hundreds of metres, and is one of the few elements in a tall building that is simultaneously a ventilation system, a fire hazard and a fire-rated compartment. It is also governed by a rule that no other duct in the building obeys: it has a minimum velocity, not just a maximum, and if the flow falls below it the grease stops travelling and starts accumulating.

1 · Why a grease riser is not a duct

2 · Interactive: hood duty and riser size

Exhaust rate follows the hood type and the appliance duty beneath it; the duct then follows from the transport velocity you choose.

Kitchen exhaust rate and grease riser diameter
Q = hood rate × hood length. Duct area = Q/v with v the design transport velocity; equivalent round diameter shown for a rectangular riser of the same area.
Open Duct sizing by velocity as a calculator
Total length of hood served by this riser.
Wall canopy: ~300 light, 400 medium, 600 heavy. Island canopies far higher.
Higher velocity = smaller duct but more fan energy and noise.
Hood to roof fan.
Exhaust rate
4.80 m³/s
Duct area
0.48
Round equivalent
782 mm
Riser friction
384 Pa
Shaft needed
1.2

A heavy-duty 8 m canopy needs 4.8 m³/s, which at 10 m/s is a 782 mm round equivalent — and once wrapped, enclosed and given clearance it consumes about 1.2 m² of shaft for the full 200 m to the roof. Push the velocity up to save shaft area and the friction climbs with the square: the same riser at 14 m/s costs roughly twice the fan pressure. Two design consequences follow. First, the shaft must be reserved from concept, because it is unbroken and cannot be re-routed later. Second, group kitchens so they can share a riser only where a fire strategy permits it — every additional independent riser is another permanent hole through the core.

3 · Interactive: the turndown trap

Kitchen exhaust is the largest single air consumer in a restaurant and an obvious candidate for demand control — hoods sense cooking activity and modulate. But grease ducts have a floor below which they stop transporting, and a variable-flow system that ignores it is building a fuel load in a shaft.

Transport velocity and fan power against exhaust turndown
Velocity falls in direct proportion to flow; fan power falls with its cube. The dashed line is the code minimum transport velocity below which grease no longer stays entrained.
Open Fan power as a calculator
Velocity at full exhaust rate. Higher design velocity buys more turndown range.
Flow as a share of design under demand control.
Code floor — around 2.5 m/s (500 fpm) in most jurisdictions.
Exhaust fan absorbed power at full flow.
Velocity now
5.0 m/s
Lowest safe turndown
25 %
Fan power now
2.8 kW
Power saved
88 %
Status

Design at 10 m/s and you can turn down to 25 % before the velocity reaches the 2.5 m/s floor — and at 50 % flow the fan is already drawing only 12 % of its design power. That is the case for demand-controlled kitchen ventilation in one line: the savings are enormous and they are available well above the safety limit. The design move that unlocks it is to choose a higher design velocity deliberately, because the turndown range you get is the ratio between design and minimum velocity. Design at 7.5 m/s and you only reach 33 %; design at 12.5 m/s and you reach 20 %. Then set the control minimum in the BMS at the velocity limit, not at the fan's minimum speed, and alarm if it is ever violated.

4 · Interactive: make-up air and what a shortfall does

Every cubic metre extracted must be replaced. If the dedicated make-up air is short, the kitchen draws the difference from wherever it can — the restaurant, the lobby, the lift shaft — and a tall building has a very large reservoir to be pulled from.

Make-up air shortfall and the resulting pressure
Shortfall = exhaust − dedicated make-up. Δp estimated by inverting Q = 0.83·A·√Δp — the EN 12101-6 / NFPA 92 form, with a discharge coefficient of 0.65 folded into the constant — across the kitchen’s leakage and door openings. The make-up air load uses the dry-air mass flow at 40 °C / 55 % RH rather than a fixed density.
Total kitchen extract including hoods and general extract.
Tempered supply provided specifically to the kitchen.
Effective area of doors, hatches and gaps between kitchen and adjacent space.
Negative pressure at which doors become hard to use and odour control fails.
Shortfall
0.72 m³/s
Kitchen pressure
−6.1 Pa
Make-up needed
4.08 m³/s
Cooling on make-up
261 kW
Status

Providing 85 % dedicated make-up leaves a 0.72 m³/s shortfall — deliberately, so the kitchen stays slightly negative and odours do not migrate into the restaurant. With a reasonable opening area that is only a few pascals, which is exactly right. Drop the make-up to 60 % and the kitchen goes strongly negative, doors become hard to open, the hoods lose capture because air is arriving sideways through the doorway rather than from the make-up plenum, and in a tall building the deficit is ultimately drawn down the lift shaft. Note the last readout: conditioning 4 m³/s of humid Gulf outdoor air is over 260 kW of cooling — which is why partially untempered or evaporatively cooled make-up air, delivered locally at the hood, is worth designing properly rather than dumping the whole load on the building's chilled water.

5 · Fire strategy for the riser

6 · Installation, cleaning & execution tricks

7 · The design & installation checklist

The one-line summary A grease riser is the only duct in the building with a minimum velocity as well as a maximum, and the ratio between your design velocity and that floor is exactly the turndown you are allowed — design at 10 m/s and demand control can take you to 25 % flow and 12 % fan power, which is an enormous saving available entirely within the safety limit. Everything else follows from the fact that it is a combustible-lined, unbroken, fire-rated shaft running hundreds of metres through occupied floors: reserve it at concept, remove as much grease as possible at the hood because that is the only place you can, design the cleaning access before the duct, and provide 80–90 % tempered make-up so the hoods actually capture and the kitchen does not end up breathing through the lift shaft.

References & standards

  1. NFPA 96 — Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations: duct construction, transport velocity, access, clearance and cleaning.
  2. ASHRAE Handbook — HVAC Applications, Kitchen Ventilation chapter — hood types, exhaust rates, capture and containment, make-up air strategies.
  3. ASHRAE Standard 154 — Ventilation for Commercial Cooking Operations; and ASTM F1704 for hood capture and containment testing.
  4. DW/172 Specification for Kitchen Ventilation Systems (BESA) — UK practice on grease duct construction, access and cleaning.
  5. BS EN 16282 series — equipment for commercial kitchens: ventilation components and design.
  6. NFPA 17A — wet chemical extinguishing systems; and UL 300 for hood suppression listing.
  7. ANSI/ASHRAE/IES Standard 90.1 — kitchen exhaust energy requirements and demand-controlled kitchen ventilation provisions.
  8. Saudi Building Code SBC 501 and SBC 801 — mechanical and fire provisions for commercial cooking operations.
#KitchenVentilation #GreaseDuct #GreaseRiser #NFPA96 #TallBuildings #MegatallBuildings #MixedUse #CommercialKitchen #Hood #CaptureAndContainment #TransportVelocity #DemandControlledKitchenVentilation #DCKV #MakeUpAir #TemperedAir #KitchenPressure #FireRatedShaft #DuctWrap #HoodSuppression #UL300 #Cleaning #AccessDoors #RoofDischarge #Dispersion #Commissioning #MEP #BuildingServices #HVAC